Construction phase

Construction Arteplage Yverdon-les-Bains

The first construction work on the Arteplage Yverdon-les-Bains began in the summer of 1999.

Construction programme

Arteplage Yverdon-les-Bains StartEnd
The Cloud - Foundation Mid 02.2001End 05.2001
The Cloud - Structures End 06.2001End 09.2001
The Cloud - Technical infrastructures Beginning 09.2001Beginning 12.2001
Expopark - Preparatory work Mid 01.2001End 03.2001
Infrastructure Expen Mid 02.2001Mid 03.2002
Expopark - Construction work Beginning 02.2001End 03.2002
Expopark - Exhibition assembly End 08.2001Mid 03.2002


Together with many contractors and people involved, work began on the construction of Expo.02.

Concept, architecture and design
Team extasia consisting of: 
Vehovar & Jauslin AG, Zurich www.vja.ch
Morphing Systems, Architektur & Ausstellungen GmbH (new: Holzer Kobler Architekturen GmbH) (Barbara Holzer, Tristan Kobler, Viola Thiele), Zurich www.holzerkobler.com 
West 8, landscape architects and urban planners b.v., Rotterdam, Netherlands www.west8.com
Diller & Scofidio, New York, United States (Authors of the Cloud) www.dsrny.com
Techdata AG, Bern (Stéphane Maye, coordination of  team extasia) www.techdata.net
Delux Theater Lighting (Rolf Derrer), Zurich

Lignting design
AIK expéditions Lumières, Paris, France
Delux Theater Lighting (Rolf Derrer), Zurich

Engineers
Emch+Berger AG, Uetendorf www.emchberger.ch

General contractor
Marti AG, Moosseedorf (piles for Cloud) www.martiag.ch
HRS Hauser Rutishauser Suter AG, Crissier (Cloud and Expopark) www.hrs.ch
Expen AG, Nidau (infrastructure)

Team Arteplage Yverdon-les-Bains Expo.02
Head of Arteplage: Noël Schneider
Debuty head of Arteplage: Reto Sulzer
Construction manager: Jean Uriot
Operations managers: Philippe Blanchoin, Marc Colin, Willy Zaugg
Exhibition managers: Sergio Cavero, Markus Röthlisberger
Head of Events: Eric Gasser
Media officers: Jacqueline Forster. Sylvie Leuthold

Photos: © Yves André; © Sottas SA, Bulle www.sottas.ch